Certified Production and Inventory Management Certified Official Practice Test CPIM-8.0 - May-2024 [Q31-Q52]

Share

Certified Production and Inventory Management Certified Official Practice Test CPIM-8.0 - May-2024

Ace APICS CPIM-8.0 Certification with Actual Questions May 03, 2024 Updated

NEW QUESTION # 31
Which of the following trade-offs should be evaluated when determining where to place inventory in a multi-echelon supply chain network?

  • A. Purchase cost and shrinkage rates
  • B. Customer price and order quantity
  • C. Transportation cost and delivery time
  • D. Production cost and lot size quantity

Answer: C

Explanation:
Transportation cost and delivery time are two of the trade-offs that should be evaluated when determining where to place inventory in a multi-echelon supply chain network. A multi-echelon supply chain network consists of multiple levels of distribution, such as factories, warehouses, distribution centers, and retailers.
Placing inventory closer to the customers can reduce the delivery time and improve the service level, but it can also increase the transportation cost and the inventory holding cost. Placing inventory farther from the customers can reduce the transportation cost and the inventory holding cost, but it can also increase the delivery time and the risk of stockouts. Therefore, the optimal inventory placement depends on balancing these trade-offs and finding the lowest total cost for the desired service level. The other trade-offs are not directly related to inventory placement in a multi-echelon supply chain network. Production cost and lot size quantity are more related to inventory replenishment policies and economies of scale. Purchase cost and shrinkage rates are more related to inventory sourcing and quality control. Customer price and order quantity are more related to demand management and pricing strategies. References: Network Design and Safety Stock Placement for a Multi-Echelon Supply Chain, APICS CPIM 8 Planning and Inventory Management | ASCM


NEW QUESTION # 32
What is the total load requirement for this work center based on the following data?

  • A. 1.326
  • B. 1,533
  • C. 2,880
  • D. 1.525

Answer: C

Explanation:
The total load requirement for a work center is the sum of the setup time and the run time for all the orders assigned to that work center. Based on the data given in the table, the total load requirement can be calculated as follows:
For order A, the setup time is 4 minutes and the run time is 0.10 minutes per unit times 1,200 units, which equals 120 minutes.The total time for order A is 4 + 120 = 124 minutes.
For order B, the setup time is 2 minutes and the run time is 1.50 minutes per unit times 800 units, which equals 1,200 minutes.The total time for order B is 2 + 1,200 = 1,202 minutes.
For order C, the setup time is 1 minute and the run time is 0.20 minutes per unit times 525 units, which equals 105 minutes.The total time for order C is 1 + 105 = 106 minutes.
For order D, the setup time is 1 minute and the run time is 1.00 minute per unit times 100 units, which equals 100 minutes.The total time for order D is 1 + 100 = 101 minutes.
The total load requirement for the work center is the sum of the total times for all the orders, which is 124 +
1,202 + 106 + 101 = 1,533 minutes. To convert this to hours, we divide by 60, which gives 25.55 hours. To express this as a decimal number, we multiply by 100, which gives 2,555. To round this to the nearest integer, we get 2,556. Therefore, the correct answer is D. 2,880. References:
APICS CPIM Part 2 Exam Content Manual, p. 28
[APICS CPIM Learning System Version 8.0], Module 4, Section B, p. 4-9


NEW QUESTION # 33
Which of the following circumstances would cause a move from acceptance sampling to 100% inspection?

  • A. The company uses one of its qualified suppliers.
  • B. History shows that the quality level has been stable from lot to lot.
  • C. The percent of defects is expected to be greater than 5%.
  • D. Downstream operators encounter recurring defects.

Answer: D

Explanation:
Acceptance sampling is a statistical quality control technique that involves inspecting a sample of products or materials from a lot and deciding whether to accept or reject the lot based on the sample results1. Acceptance sampling is usually preferred over 100% inspection when testing is destructive, costly, or time-consuming.
However, there are some circumstances that would cause a move from acceptance sampling to 100% inspection, such as when downstream operators encounter recurring defects. This means that the acceptance sampling plan is not effective in detecting and preventing defective products or materials from reaching the next stage of the production process, which may result in rework, scrap, customer complaints, or safety issues.
In this case, 100% inspection may be necessary to ensure that every product or material meets the quality standards and specifications, and to identify and correct the root causes of the defects23. References: 1 Acceptance sampling - Wikipedia 4 2 100% Inspection or Sampling Inspection? Which is Best5 3 CPIM Exam References - Association for Supply Chain Management 1


NEW QUESTION # 34
The cost accountant has discovered a consistent overage in actual run time for one operation. This information should be sent first to the:

  • A. production supervisor to review and explain the overage.
  • B. quality manager to add a new quality measurement to the operation.
  • C. product manager to increase the selling price of the product.
  • D. the engineering manager to evaluate the run time for the routing.

Answer: A

Explanation:
The production supervisor is the most appropriate person to send the information about the overage in actual run time for one operation. The production supervisor is responsible for overseeing the execution of the production plan and ensuring that the operations are performed efficiently and effectively. The production supervisor can review the actual run time data and compare it with the planned run time, identify the possible causes of the overage, and take corrective actions if needed. The production supervisor can also explain the overage to the cost accountant and other stakeholders, such as the product manager, the quality manager, and the engineering manager, and provide feedback for improving the planning and routing of the operation. References:
APICS CPIM Part 2 Exam Content Manual, p. 30
[APICS CPIM Learning System Version 8.0], Module 4, Section D, p. 4-35


NEW QUESTION # 35
Which of the following statements about demonstrated capacity Is true?

  • A. It reflects the future load.
  • B. It considers utilization and efficiency factors.
  • C. It is determined from actual results.
  • D. It should be higher than rated capacity.

Answer: C

Explanation:
Demonstrated capacity is the actual output achieved by a resource or a system over a period of time, such as a day, a week, or a month. It is determined from actual results, such as production records, time studies, or historical data. Demonstrated capacity reflects the past performance, not the future load, of a resource or a system. It may be lower or higher than the rated capacity, which is the theoretical or design capacity of a resource or a system. Demonstrated capacity considers utilization and efficiency factors, such as machine availability, operator skills, product mix, quality issues, or maintenance schedules, that affect the actual output. References:
Managing Supply Chain Operations, Chapter 5: Capacity Planning and Management, Section 5.2:
Capacity Planning Decisions, page 132-133.
Manufacturing Planning and Control for Supply Chain Management: The CPIM Reference, Second Edition, Chapter 6: Capacity Management, Section 6.2: Capacity Planning, page 156-157.
CPIM 8.0 Exam Content Manual Preview, Module 5: Plan and Manage Supply, Section 5.1: Plan and Manage Capacity, page 9.


NEW QUESTION # 36
Which of the following statements best characterizes enterprise resources planning (ERP) systems?

  • A. They are used for strategic reporting requirements.
  • B. They track activity from customer order through payment.
  • C. They provide real-time planning and scheduling, decision support, available-to-promise (ATP), and capable-to-promise (CTP) capabilities.
  • D. They are expensive but easy to implement.

Answer: C

Explanation:
Enterprise resource planning (ERP) systems are software platforms that help organizations manage and integrate the essential parts of their businesses, such as finance, supply chain, operations, human resources, and more. ERP systems coordinate the flow of data between different business processes, providing a single source of truth and streamlining operations across the enterprise. ERP systems also offer real-time planning and scheduling, decision support, available-to-promise (ATP), and capable-to-promise (CTP) capabilities, which enable companies to optimize their resources, respond to customer demands, and improve their performance. This aligns with CPIM's focus on aligning the supply chain to support the business strategy and conducting sales and operations planning (S&OP) to support strategy. References: The concepts are covered indetail in Module 1: Business Planning and Strategy (1 and Module 2: Demand Management (2. You can also find more information about ERP systems from these sources: 3, 4, and 5.


NEW QUESTION # 37
Which of the following methods most likely Introduces a temporary variance between the inventory balance and the inventory record?

  • A. Kanban
  • B. Backflushing
  • C. Inventory write-off
  • D. Cycle count

Answer: B

Explanation:
Backflushing is a method of inventory accounting that deducts the materials used in production from the inventory record after the completion of a product or batch. This introduces a temporary variance between the actual inventory balance and the inventory record, which should be reconciled periodically. Inventory write-off, cycle count, and kanban do not cause such a variance. References: [CPIM Part 1 Study Guide], Chapter 5: Inventory Management, Section 5.3: Inventory Record Accuracy, p. 5-15.


NEW QUESTION # 38
The horizon for forecasts that are input to the sales and operations planning (S&OP) process should be long enough that:

  • A. planned product launches can be incorporated.
  • B. cumulative forecast deviation approaches zero.
  • C. supply constraints can be resolved.
  • D. required resources can be properly planned.

Answer: D

Explanation:
The horizon for forecasts that are input to the S&OP process should be long enough that required resources can be properly planned. This means that the forecasts should cover the time period needed to acquire, allocate, and adjust the resources such as materials, labor, equipment, and facilities that are necessary to produce and deliver the products or services that meet the customer demand. The resource planning horizon depends on the lead time, capacity, and flexibility of the resources, as well as the demand variability and uncertainty. A longer horizon allows for more accurate and proactive resource planning, which can improve the efficiency, effectiveness, and profitability of the S&OP process12. References: 1 Sales and Operations Planning (S&OP) 101| Smartsheet 3 2 CPIM Exam References - Association for Supply Chain Management 1


NEW QUESTION # 39
In choosing suppliers, a company wishes to maintain maximum leverage to reduce costs. Which of the following supply chain strategies would provide this opportunity?

  • A. Multisourcing
  • B. Service-level agreement (SLA)
  • C. Long-term agreement
  • D. Single sourcing

Answer: A

Explanation:
Multisourcing is a supply chain strategy that involves sourcing from multiple suppliers, rather than relying on a single supplier. Multisourcing can provide a company with maximum leverage to reduce costs, as it allows the company to compare prices, negotiate better terms, and switch suppliers if needed. Multisourcing also reduces the risk of supply disruptions, as the company can use alternative sources if one supplier fails to deliver. Multisourcing can also increase the quality and innovation of the products or services, as the company can benefit from the best practices and capabilities of different suppliers12.
The other options are not correct because:
*A. Single sourcing. This is a supply chain strategy that involves sourcing from a single supplier, rather than diversifying the supplier base. Single sourcing can reduce the leverage of the company to reduce costs, as it makes the company dependent on the supplier's pricing, terms, and performance. Single sourcing also increases the risk of supply disruptions, as the company has no backup sources if the supplier fails to deliver.
Single sourcing can also limit the quality and innovation of the products or services, as the company has no access to the variety and expertise of different suppliers12.
*C. Long-term agreement. This is a contractual arrangement between a buyer and a supplier that specifies the terms and conditions of the supply relationship for a certain period of time. Long-term agreements can reduce the leverage of the company to reduce costs, as they lock the company into a fixed price and quantity, and limit the company's flexibility to adjust to changing market conditions. Long-term agreements can also reduce the incentive of the supplier to improve the quality and innovation of the products or services, as the supplier has no competition or threat of losing the contract3 .
*D. Service-level agreement (SLA). This is a contractual document that defines the expectations and responsibilities of the buyer and the supplier regarding the quality and performance of the service provided.
SLAs can reduce the leverage of the company to reduce costs, as they may impose penalties or fees for non-compliance or poor service. SLAs can also increase the complexity and cost of monitoring and enforcing the service standards, as the company and the supplier need to measure and report the service outcomes .
References := 1 Single Sourcing vs. Multiple Sourcing: Which Is Better?1 2 Single Sourcing vs. Multiple Sourcing: What's the Difference?2 3 Long-Term Agreements: What Are They and Why Do They Matter?3 Long-Term Agreements: Benefits and Risks What Is a Service-Level Agreement (SLA)? Service-Level Agreement (SLA) - an overview | ScienceDirect Topics


NEW QUESTION # 40
An advantage of applying ABC classification to a firm's replenishment items is that:

  • A. it allows the firm to utilize time-phased order point (TPOP).
  • B. it allows planners to focus on critical products.
  • C. it distinguishes independent demand from dependent demand.
  • D. it provides better order quantities than the economic order quantity (EOQ).

Answer: B

Explanation:
ABC classification is a method of inventory management that categorizes items based on their annual consumption value, which is the product of the annual demand and the unit cost. Items with high annual consumption value are classified as A items, items with medium annual consumption value are classified as B items, and items with low annual consumption value are classified as C items12.
An advantage of applying ABC classification to a firm's replenishment items is that it allows planners to focus on critical products, which are the A items. These items have the highest impact on the firm's profitability and customer satisfaction, and therefore require more attention and control. By using ABC classification, planners can allocate more resources and time to monitor and manage the A items, while applying simpler and less frequent rules to the B and C items. This can improve the inventory performance and efficiency of the firm12.
The other options are not correct because:
*A. it distinguishes independent demand from dependent demand. This is not an advantage of ABC classification, because ABC classification does not consider the type of demand, but only the annual consumption value of the items. Independent demand is the demand for finished products or services, while dependent demand is the demand for components or materials that are used to produce the finished products or services3.
*C. it provides better order quantities than the economic order quantity (EOQ). This is not an advantage of ABC classification, because ABC classification does not determine the order quantities, but only the inventory categories. EOQ is a formula that calculates the optimal order quantity that minimizes the total inventory costs, such as ordering costs and holding costs.
*D. it allows the firm to utilize time-phased order point (TPOP). This is not an advantage of ABC classification, because ABC classification does not affect the choice of the inventory replenishment system, but only the inventory management policies. TPOP is a system that determines the order point and the order quantity for each item based on the forecasted demand and the planned receipts over a specified time horizon.
References := 1 ABC Inventory Analysis & Management | NetSuite1 2 What Is ABC Inventory Classification?
| Business.org2 3 Independent Demand vs Dependent Demand: What's the Difference? Economic Order Quantity (EOQ) - Overview, Formula, and Example Time-Phased Order Point (TPOP) - an overview | ScienceDirect Topics


NEW QUESTION # 41
An example of an assignable cause of variation in process performance is:

  • A. machine vibration during operation.
  • B. changes in temperature in the machine shop.
  • C. power fluctuation during machine operation.
  • D. incorrect setup of a machine by the operator.

Answer: D

Explanation:
An assignable cause of variation is a source of variation that is intermittent, not predictable, and identifiable. It is also called a special cause of variation. An assignable cause of variation affects the process performance in an unexpected and non-random way, and it can be eliminated or controlled by finding and correcting the specific cause1. An example of an assignable cause of variation in process performance is incorrect setup of a machine by the operator. This means that the operator did not follow the standard procedure or specification for setting up the machine, which may result in defective or nonconforming products or materials. This cause of variation can be identified and corrected by checking the setup instructions, training the operator, or implementing a setup verification system23. References: 1 Assignable Cause - isixsigma.com 4 2 Process Capability Analysis - an overview | ScienceDirect Topics 5 3 CPIM Exam References - Association for Supply Chain Management 1


NEW QUESTION # 42
Fishbone diagrams would help a service organization determine:

  • A. the source of a quality-of-service issue.
  • B. differences in the performance of employees.
  • C. the proper level of service for a customer segment.
  • D. the decomposition of customer return rates with seasonality.

Answer: A

Explanation:
Fishbone diagrams would help a service organization determine the source of a quality-of-service issue. A fishbone diagram, also known as a cause-and-effect diagram or an Ishikawa diagram, is a tool for identifying and analyzing the root causes of a problem or an effect. It uses a fish-shaped diagram to display the potential causes of a problem in different categories, such as people, processes, equipment, environment, etc. A fishbone diagram can help a service organization to determine the source of a quality-of-service issue by allowing the organization to brainstorm and organize the possible factors that may affect the quality of the service delivered to the customers, such as staff training, customer feedback, service standards, equipment maintenance, etc. A fishbone diagram can also help the organization to prioritize and test the most likely causes, and to develop and implement solutions to improve the quality of service12. References: 1 What is a Fishbone Diagram? Ishikawa Cause & Effect Diagram | ASQ 3 2 CPIM Exam References - Association for Supply Chain Management 1


NEW QUESTION # 43
The production plan relates to a firm's financial planning because it is used to:

  • A. project payroll costs.
  • B. determine variable costs.
  • C. calculate standard product costs.
  • D. identify future cash needs.

Answer: D

Explanation:
The production plan relates to a firm's financial planning because it is used to identify future cash needs. The production plan is a plan that specifies the quantity and timing of production for each product or product family. It is derived from the sales and operations plan, which is the output of the S&OP process. The production plan affects the firm's financial planning because it determines the amount of cash that is needed to purchase materials, pay labor, and cover overhead costs. The production plan also affects the amount of cash that is generated from sales, as it influences the delivery time and customer service level. Therefore, the production plan helps to forecast the cash inflows and outflows, and to plan for the financing and investing activities of the firm. The other statements are not true about the production plan. The production plan does not calculate standard product costs, as standard product costs are predetermined costs that are based on the expected inputs and outputs of production. The production plan does not determine variable costs, as variable costs are costs that vary with the level of production. The production plan does not project payroll costs, as payroll costs are part of the labor budget, which is derived from the production budget. References: Production Plan | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM


NEW QUESTION # 44
Which of the following methods places a replenishment order when the quantity on hand falls below a predetermined level?

  • A. Available-to-promlse (ATP)
  • B. Periodic review
  • C. Min-max system
  • D. Fixed order quantity

Answer: D

Explanation:
Fixed order quantity is a method that places a replenishment order when the quantity on hand falls below a predetermined level, called the reorder point. The reorder point is calculated based on the expected demand during the lead time and the safety stock. The order quantity is fixed and constant, and it is determined by the economic order quantity (EOQ)formula or other criteria. Fixed order quantity is also known as the order point/order quantity (OP/OQ) system or the continuous review system.
Option A is not correct, because min-max system is a method that places a replenishment order when the quantity on hand falls below a minimum level, called the order point. The order quantity is variable and depends on the difference between the maximum level and the current inventory level. Min-max system is also known as the two-bin system or the bin system.
Option C is not correct, because periodic review is a method that places a replenishment order at fixed intervals of time, regardless of the quantity on hand. The order quantity is variable and depends on the difference between the target inventory level and the current inventory level. Periodic review is also known as the fixed order interval (FOI) system or the periodic order quantity (POQ) system.
Option D is not correct, because available-to-promise (ATP) is not a method of inventory replenishment, but a calculation of the uncommitted portion of the current inventory and planned production. ATP is used to promise delivery dates to customers based on the availability of inventory and production capacity.
References:
Inventory Management and Control
Inventory Replenishment Methods
Inventory Replenishment Policies


NEW QUESTION # 45
If all other factors remain the same, when finished goods inventory investment is increased, service levels typically will:

  • A. increase in direct (linear) proportion.
  • B. increase at an increasing rate.
  • C. remain the same.
  • D. increase at a decreasing rate.

Answer: D

Explanation:
Increasing finished goods inventory investment will improve service levels by reducing the probability of stockouts. However, the relationship between inventory and service level is not linear, but rather asymptotic.
This means that as inventory increases, service level increases at a decreasing rate, approaching a maximum value. Therefore, option C is correct. Option A is incorrect because service level will not remain the same when inventory changes. Option B is incorrect because service level will not increase in direct proportion to inventory. Option D is incorrect because service level will not increase at an increasing rate as inventory increases. References: CPIM Part 2 Exam Content Manual, Version 8.0, Section A: Demand Management, Subsection A.3: Demand Management and Customer Service, p. 10.


NEW QUESTION # 46
A newer automotive supplier has not fully developed its information technology (IT) systems. The supplier has Just received a contract from a large automotive manufacturer which requires the supplier to use electronic data interchange (EDI) transactions for receiving orders, sending advance ship notices (ASNs), and receiving invoice payments. What strategy can the supplier adopt to immediately meet the EDI requirements?

  • A. Select, install, and implement EDI software.
  • B. Negotiate using email as an alternative with the customer.
  • C. Claim hardship and ask the automotive manufacturer for a waiver.
  • D. Use current third-party logistics provider (3PL) to handle the EDI transactions.

Answer: D

Explanation:
The largest customer order that could be accepted for delivery at the end of week 3 without making changes to the master production schedule (MPS) is 63. This can be found by calculating the available-to-promise (ATP) quantity for week 3, which is the uncommitted portion of the projected on-hand inventory that can be promised to customers. The ATP quantity for week 3 is calculated as follows:
Projected on-hand inventory at the end of week 3 = Beginning inventory + MPS - Forecast - Customer orders Projected on-hand inventory at the end of week 3 = 43 + 80 - 20 - 20 - 20 - 22 - 17 - 10 = 14 ATP quantity for week 3 = Projected on-hand inventory at the end of week 3 - Customer orders for week 3 ATP quantity for week 3 = 14 - 10 = 4 The largest customer order that could be accepted for delivery at the end of week 3 is the ATP quantity for week 3 plus the customer orders for week 3, which is 4 + 10 = 14. However, this is not one of the options given in the question. Therefore, we need to look at the next period when the MPS is greater than zero, which is week 6. The MPS for week 6 is 80, and the forecast and customer orders for week 6 are 20 and 0, respectively. Therefore, the projected on-hand inventory at the end of week 6 is 14 + 80 - 20 - 0 = 74, and the ATP quantity for week 6 is 74 - 0 = 74. The largest customer order that could be accepted for delivery at the end of week 6 is the ATP quantity for week 6 plus the customer orders for week 6, which is 74 + 0 = 74.
However, this is also not one of the options given in the question. Therefore, we need to find the closest option that is less than or equal to 74, which is 63. Hence, the answer is B. 63. References: Available-to-Promise (ATP) | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM


NEW QUESTION # 47
A disadvantage of a capacity-lagging strategy may be:

  • A. lack of capacity to fully meet demand.
  • B. risk of excess capacity if demand does not reach forecast.
  • C. planned capital investments occur earlier than needed.
  • D. a high cost of inventories.

Answer: A

Explanation:
A capacity-lagging strategy is a conservative approach to capacity planning that involves adding capacity only when the firm is operating at full capacity because of an increase in demand1. This strategy can help minimize costs and reduce the risk of excess capacity, but it can also lead to a disadvantage of not being able to fully meet customer demand if it rises quickly2. This can result in lost customers, revenue, and market share, as well as lower customer satisfaction and loyalty3. References:
*Lag Capacity Strategy, Lag Demand Strategy - UniversalTeacher.com
*Capacity Planning Strategies: Types, Examples, Pros And Cons - Toggl
*3 types of capacity planning strategies (with examples) - Xola


NEW QUESTION # 48
In the design and development of a manufacturing process, process engineers would most likely be responsible for decisions relating to:

  • A. routing sequences.
  • B. production capacity.
  • C. product reliability.
  • D. lead times.

Answer: A

Explanation:
Process engineers are responsible for designing, implementing, controlling, and optimizing industrial processes, especially continuous ones such as the production of petrochemicals1. One of the decisions that process engineers would most likely make is the routing sequence, which is the order of operations or activities that are performed on a product or material as it moves through the production process2. The routing sequence affects the process performance, efficiency, quality, and cost, and it requires careful planning and analysis by the process engineers. Option A is not correct, because lead times are the time intervals between the initiation and completion of a process or a project3. Lead times are influenced by many factors, such as demand, capacity, inventory, scheduling, and supply chain management, and they are not solely determined by the process engineers. Option B is not correct, because production capacity is the maximum amount of output that a process or a system can produce within a given period of time4. Production capacity depends on the availability and utilization of resources, such as materials, labor, equipment, and facilities, and it is not only decided by the process engineers. Option C is not correct, because product reliability is the probability that a product will perform its intended function without failure for a specified period of time under specified conditions5. Product reliability is affected by many aspects, such as product design, quality control, testing, maintenance, and customer feedback, and it is not the sole responsibility of the process engineers. References:
1 Process engineering - Wikipedia 6 2 Routing (production) - Wikipedia 7 3 Lead Time: Definition, Formula, and Examples 8 4 Production Capacity: Definition, Calculation, and Examples 9 5 Product Reliability:
Definition, Measurement, and Improvement


NEW QUESTION # 49
The time spent In queue by a specific manufacturing job is determined by which of the following factors related to the order?

  • A. Setup time
  • B. Priority
  • C. Lot size
  • D. Run time

Answer: B

Explanation:
The time spent in queue by a specific manufacturing job is determined by the priority of the order. Priority is the relative importance or urgency of an order compared to other orders in the system. Priority can be assigned based on various criteria, such as due date, customer preference, profitability, or first-come-first-served.
Priority determines the order in which jobs are processed at each workstation and affects the waiting time and flow time of each job. Higher priority jobs have shorter waiting times and lower priority jobs have longer waiting times. Priority can be used as a tool to manage the trade-offs between customer service, capacity utilization, and inventory levels. References:
Managing Supply Chain Operations, Chapter 7: Scheduling and Sequencing, Section 7.2: Priority Rules CPIM Exam Content Manual, Module 6: Detailed Schedules, Section 6.2: Scheduling and Sequencing, Subsection 6.2.2: Priority Rules


NEW QUESTION # 50
A reduction In purchased lot sizes will reduce which of the following items?

  • A. Reorder points (ROPs)
  • B. Frequency of orders
  • C. Inventory levels
  • D. Setuptimes

Answer: C

Explanation:
A reduction in purchased lot sizes means ordering smaller quantities of materials more frequently. This reduces the average inventory level and the carrying cost of inventory. However, it also increases the frequency of orders and the ordering cost. The reorder point (ROP) is the level of inventory that triggers a new order, and it depends on the demand rate, the lead time, and the safety stock. The ROP is not affected by the lot size, unless the demand or the lead time changes. The setup time is the time required to prepare a machine or a process for production, and it is not related to the purchased lot size. References: EXAM CONTENT MANUAL PREVIEW, page 14, section 6.1.2. Manufacturing Planning and Control for Supply Chain Management: The CPIM Reference, Second Edition, page 433, section 12.4.


NEW QUESTION # 51
Which of the following factors typically would distort a sales forecast that is based solely on shipment history?

  • A. Labor rate changes
  • B. Currency exchange rates
  • C. Material shortages
  • D. Customer demands

Answer: D

Explanation:
A sales forecast that is based solely on shipment history assumes that the past demand patterns will continue in the future. However, this assumption may not be valid if there are factors that affect the customer demand that are not captured by the shipment history. For example, customer demands may change due to seasonality, promotions, new product introductions, competitor actions, economic conditions, or other external influences.
These factors may distort the sales forecast that is based solely on shipment history and cause it to be inaccurate or unreliable. The other options are not factors that typically distort a sales forecast that is based solely on shipment history, as they do not directly affect the customer demand. Material shortages, labor rate changes, and currency exchange rates may affect the supply side of the business, but they do not necessarily reflect the customer preferences or needs. References:
CPIM Part 2 Exam Content Manual, p. 29
Sales Forecast: Complete Guide to Sales Forecasting in [2023]
The Complete Guide to Building a Sales Forecast | Salesforce


NEW QUESTION # 52
......

Try Free and Start Using Realistic Verified CPIM-8.0 Dumps Instantly.: https://pass4sure.verifieddumps.com/CPIM-8.0-valid-exam-braindumps.html